Rain is still sl0wing us down. But we’ve made some progress. The house is fully taped. Rob’s guys are preparing it for the blower door test on Monday, buy installing the basement door and caulking and caulking. Being sheathed with no windows makes it very dark inside, thus it’s easy to see light coming in any openings. The front step arrive tomorrow. The garage is prepped for the floor to be poured tomorrow. And my work vehicle has arrived. Once the blower door test is done we start the roof, followed by the siding……….