Blower Door Test 0.5ACH50

Friday after the insulation was complete Ken did a blower door test.  It’s taken me 2 years of research to get to under stand what XX ACH50 means, and what tight mean for a house.  For those who are just learning I’ll try to explain.

You start by closing the house up tight, windows & door closed, plumbing vents, sump vents and so on are taped shut.  A box with a fan is mounted in the front door.  See photos.103 Blower Door Test (4) 103 Blower Door Test (2)

The fan is run to depressurize  the house to 50 Pascal’s. The fan is controlled by a device that measures the difference in pressure of the outside to the inside of the house.  It was having trouble holding on the 50 Pascal’s,  note the black disks in the holes around the fan.  Ken had to add a couple more to get the fan to settle down.  My guess that is because the house is so tight.

There are many articles online about house tightness and blower door testing.  As a reference for you,  the 2015 Code will require all house to achieve a “3 ACH50” .  That’s 3 full house Air Changes per Hour at 50 Pascal’s of depressurization.  NJ has adapted the 2015 code effective March 2016,  but not the 3 ACH50 requirement.  Pulte the 4 largest builder in the US has announced they will build a High performance model in CA this spring with a 3.5 ACH50 target.  It is the future, but the future isn’t here in a big scale yet.

Our reading Friday was an 0.5 ACH50.  I think that is about as tight as a house can get. That means the fan can only suck half the full volume of the air of the house in an hour. Here is the gage.  It shows at    -50.1 Pascals the fan is sucking out 401 CFM, the full house volume is 46,251 CF. All I can say is success.  That’s 600% better than code.    ( and one builder told me I’m reading to much)   🙂

103 Blower Door Test (3)

2 thoughts on “Blower Door Test 0.5ACH50

  1. I’ve done hundreds of blower door tests and never used the C8 or C6 or C4 range before. I needed to use C2 on this job. It was even better than we had expected and mostly because we paid attention to the details from the start and Ed had every contractor in the place on board with the goals from the very beginning.

    Like

Leave a Reply to Ken Field Cancel reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s